The tldr
> If we look at our Fastest MW analysis, the fastest way to get power to the grid right now is solar+BESS with existing interconnection agreements in ERCOT. This setup gives a 27-month or less time-to-COD, and can come in at $40/MWh PPAs, a price and speed Fervo can't catch. So, per the above, the right way to think about it is that Fervo competes for a different customer than the ones looking at solar+BESS. Are they required to procure geo? Are they in the West? Do they need fully baseload power? For sure, that’s a smaller niche. But if Fervo's anticipated 38GW resource base materializes even a little, the niche is huge.