Inconel is through the roof and I know a few aerospace clients who are MONTHS behind due to shortages and bonkers material costs. Like holding up the military supply chain which is ludicrous. This admin is brain dead.
Inconel is through the roof and I know a few aerospace clients who are MONTHS behind due to shortages and bonkers material costs. Like holding up the military supply chain which is ludicrous. This admin is brain dead.
Same too with customers. The people buying bulk metal need is when they need it. They don't want to wait around, literally, for the winds to change.
The aluminium smelters I've had contact with have all avoided any shutdowns (back up generators, etc) because any significant breakdown in continuous processing involves several days of tear down in order to restart.
I am literally within 20 feet of someone who worked 5 years as a general foreman in charge of the smelter portion of the Portland aluminium smelter* who is not embracing the idea that this a process you can just turn off and turn on again later w/out a large chunk of effort.
I think at a steel smelter, since the heat does the work, they aren't as easily separable. You would still use less energy at the times when you processed less metal.
Aluminium smelters were traditionally some of the biggest loads on the grid. They were built near hydroelectric dams and had contracts with electricity providers to absorb excess energy and to pause operations on short notice when other demand is high. In exchange for this they get it very cheap, which is good because they need a lot of it. Variable energy supply is not new to them.
Now I've never worked at either and I'm just spitballing ideas on the internet, but you haven't either and you are too.