Storage? Even that is now ultra-compact.
Storage? Even that is now ultra-compact.
Figure on ~10 million square feet of conditioned DC space per year, approximately 5-10GW of additional power consumption to power those 250k cabinets (depending on the exact mixture of what’s in the racks — Compute, Storage, Network, Accelerators), and that’s just for one hyperscaler.
There are at least 5-7 companies in the hyperscaler weight class although likely none individually meaningfully larger than AWS, they’re the 800lb bear and everyone else is in the 500-750lb range.
It’s a lot. Datacenters also take long enough to build that a hyperscaler is pouring concrete today for shells they expect to serve real workloads in 2029 - 2031. What you’re seeing come online today in response to customer demand really started being built in 2021 - 2023.