If not, what would these AI companies do with the huge supply of hardware they're going to want to get rid of? I think a secondary market is sure to appear.
If not, what would these AI companies do with the huge supply of hardware they're going to want to get rid of? I think a secondary market is sure to appear.
These are not the old CPU servers of yesterday.
Then you'd have to deal with noise from a literal wall of fans, or build a separate high capacity water cooling system (and still deal with dumping that heat somewhere).
I’ve heard stories about people convincing their utility to install three-phase service drops in their homes, but usually it’s not an option.
Anyways, 320A continuous load at 240V single-phase is 76.8kW, if you assume 25kW per server (20 kW for server, 5kW for cooling), you can run (3) servers and 15 tons of cooling and still have just enough left for one 120V 15A circuit to charge your phone and power a light.