You can build a tract of homes in 90 days (or less) using stick frame. They won't be fancy, but they'll be up to code (and with a little extra cost (<10%) and effort, they can be made much more efficient than just code).
A crew of 4-5 guys (plus some subs) can build a custon home in 80 days:
* https://www.youtube.com/watch?v=LYd73YP57Ik&list=PL8XEQ1XKYN...
If you pipeline that and use a standardized, cookie-cutter plan an entire row can be build out in a similar time frame. Production builders do it all the time:
* https://www.newhomesource.com/learn/custom-or-production-bui...
There are of course mass-manufactured elements that can speed things up, like using trusses. There are also now services for pre-cut framing that saves on-site effor of measuring and such:
* https://www.youtube.com/watch?v=o2FdAdxjSpw&list=PLDYh81z-Rh...
The building of the structure is not the bottleneck, it is the approval process and NIMBY road blocks that can add 2(+) years to a project.