Maybe new boring machines are faster and cheaper and break down less than before.
Maybe new boring machines are faster and cheaper and break down less than before.
But the externalities of cut and cover can be very expensive (blocks streets, and hurts nearby businessen even to the point of going out of business). Those second order effects, even if transient on a long term scale, can cause expensive hold ups. Other externalities are the need to get around existing infrastructure, some of which could have over a century of continuous use.
So for example in NY it is almost impossible (look at the 2nd ave subway, which is mostly pretty shallow) while in LA cut and cover was no problem at all.
Businesses should take risks. However government should not add extra risk without careful consideration.
I'm talking about the US here -- no idea elsewhere.
Is it more or less disruptive if you do a checkerboard pattern instead? Instead of n months of construction around your favorite coffee shop, would it be better to have n/2 months of construction now, and n/2 months of construction in July? Maybe that depends on where you are on the street. If, for instance, you start at both ends, then the businesses in the middle of the cut have construction sites boxing them in for almost twice as long as anyone else does. Or maybe that just means more people of means mad at elected officials.
If you could build the entire thing in 2 weeks (per year) people would be happy with a full road closure - they would all take vacation for those two weeks. This is for the entire city - close all roads to non-emergency traffic for two weeks, fix them all up - everyone not involved in road work or essential services would just go on vacation. You cannot do this of course, but that is what people really want.
I recall when South Lake Union got its trolley, one of the things they pointed out was that property values next to a trolley drop, but property values 1 block away go up more. Everyone wants to be a couple blocks from transit, not living above it. So even if you avoided the main road going parallel to it, you're probably tearing up even more desirable real estate and commercial zoning.
When you ignore all the side effects, sure (especially if you also ignore the risks of blowing the timeline).
Trenchless tech is spreading fast even in small-ish (street utility scale) construction.
> Maybe new boring machines are faster and cheaper than they used to be.
I'm not sure that's even the case, AFAIK TBMs are still custom-built for the job, highly geology-dependent, and require a ton of babysitting. If you hit an unexpected patch of really different geology things can get really dicey.
This is semi-true. They are built for the job, but the design is standard. What is custom is the exact size of the tunnel, and thus all the supports.
TBMs generally last a lot longer than the job, so a city could save a lot of money if they planed to keep using their TBM, constantly digging tunnels. Start with a north-south line, then use the same TBM to build an east-west line (or southeast/northwest), and so on. However most cities are unable to find the continuous budget to do that and so when they are ready for the next one the old TBM is no longer worth using, and in any case they no longer have trained crew to run it.
> highly geology-dependent,
Soft water logged earth needs different machines from hard rock. There are combination machines, but if you can determine which you need you save a lot of money ordering the geology specific machine. Get this wrong and you end up with a TBM and partial tunnel under the city.
> require a ton of babysitting.
12 people per shift is the number I've heard (NYC uses double which is one of the smaller reasons things cost so much there). The work is mostly routine though. However the TBMs do break once in a while and they everything stops while you repair them.
Think about every time you've been stuck in traffic because there are 3 roads that get you from A to B, and some jackass at city hall thought it would be a good idea to permit road work on 2 of them on the same day.
We are used to highway on-ramps being replaced in days to weeks, but removing an entire street, digging up everything under it, being careful not to nick the utility lines and pipes, then packing dirt back in around them without tearing them, then rebuilding the street on top, that's a lot. Especially for the businesses on that road.
We end up with transportation solutions that are suboptimal because we don't have the political will to tear off the bandaid. This on-ramp is in the wrong place because the old one was in the right place, but was built in a terrible way and had to be removed for safety while still handling daily commutes.
It helps when you can complete the project in a few years and not take a decade to build out a single line. So politics does have an impact on feasibility and practicality of C&C.