According to the tweets, researchers who reserved time for their projects on the supercomputer had to sign NDAs so they cannot complain about the delays... not exactly a good look.
> The U.S. should have had two exascale supercomputers on the Top 500 in 2021. And Aurora, which has been plagued by Intel’s delays since 2017, should have been first—well before “Frontier” at Oak Ridge National Lab appeared. But Intel dropped the ball over. And over. And again.
It does acknowledge that recent deliveries will allow the project to place on the current supercomputer list by virtue of finally being able to run LINPACK tests ... but that's still a few years late and well short of what was promised to be delivered, tested, bedded, and deep into working by now.
https://insidehpc.com/2020/08/exascale-exasperation-why-doe-...