> Phase 1 of Moss Landing Energy Storage Facility was connected to the power grid and began operating on 11 December 2020, at the site of Moss Landing Power Plant, a natural gas power station owned by Vistra since it acquired the facility’s previous owner, Dynegy in 2018.
> At 300MW / 1,200MWh, the BESS is considerably larger than the 250MW / 250MWh Gateway Energy Storage project brought online earlier this year by LS Power, also in California. Not only that, but Phase 2 of Vistra’s project will add another 100MW / 400MWh and is scheduled for completion by August this year.
> The site at Moss Landing then offers what Vistra called a “unique opportunity” to expand the project’s size and storage capacity even further: the company claimed that the industrial zone in which it sits offers the potential to support up to 1,500MW / 6,000MWh of energy storage capacity, “should market and economic conditions support it”.
https://www.energy-storage.news/news/at-300mw-1200mwh-the-wo...