Generally, SCADA, AGC, and any EMS software updates should go through multiple lower environments before getting into a production environment. Even critical patches would spend a little bit if time in a lower environment prior to production.
AGC just balances power flows so imports/exports over interconnections between power authorities flow as scheduled right?
It's rare for an org (and usually only very large heavily regulated government orgs) do full testing on new builds.