Very interesting graph, thanks for sharing. I guess the point of the graph is that the progress in fusion has been steady and followed an exponential low for 3 decades, in a way that matches the Moore law.
If I were a politician in 2019 with the right to sign funding and I see this graph, I cut all funding right away. Here's why:
* based on this graph, a simple extrapolation by only 2 years show the achievement of the commercial reactor in 2005. Where's the commercial reactor 14 years later? We are instead only 6.5 years away before pushing a certain button at ITER, which has some type of significance that's not entirely clear
* at least one point on this graph is "cooked": the JT-60U that appears to cross the breakeven point at some point prior to 2000. Here's what wikipedia [1] says about this:
"During deuterium (D–D fuel) plasma experiments in 1998, plasma conditions were achieved which would have achieved break-even—the point where the power produced by the fusion reactions equals the power supplied to operate the machine—if the D–D fuel were replaced with a 1:1 mix of deuterium and tritium (D–T fuel)."
What's the point of the "figure-of-merit" graph then? It projects when we'll get to breakeven or commercial, only to find there that you need to make another tiny change (i.e. substitute D with T) that will take 30 more years?
[1] https://en.wikipedia.org/wiki/JT-60#JT-60U_(Upgrade)