I complained about daily reporting and my senior said I can say I could not achieve anything in a day, but I have to report. I haven't done that any time. Can anyone here advise if it's fine for me to report that.
I complained about daily reporting and my senior said I can say I could not achieve anything in a day, but I have to report. I haven't done that any time. Can anyone here advise if it's fine for me to report that.
I think that deliberately making a to-be-scrapped system just to generate some work-done for the report is a waste of your time and you'd be better just making the real progress you can within the day and then reporting on how it's going/what (if anything) is stopping you from making progress; in general I don't think that tasks which take more than a day are expected to be complete.
The report is really about making sure that you're not sitting there unable to make any progress for days/weeks/months at a time resulting in an unexpected failure to deliver at the other end.
HTH.