Maybe at the 100MW scale it already operates like this, but not at smaller scale. Recently I had a discussion with a county level public utility district where we were exploring building a 1-10 MW Solar system on a closed landfill. The capability existed for us to wheel the power to a load that was interested in the energy, but the smallest chunk of capacity we could buy was 1MW and the cost to wheel the power would require a >90% capacity factor to make it economical.
So the system may well exist, but I think there is benefit from some scaling down of the market rules.