[1] http://www.nrc.gov/waste/decommissioning/finan-assur.html
[1] http://www.nrc.gov/waste/decommissioning/finan-assur.html
They are supposed to. But here in germany the energy company lobbists basically said - in response to a few new proposed fees levied on coal plants - that anything threatening their revenues would cut into future revenue needed for decommissioning fees. And that's despite being required to have funds set aside for decommissioning.
I suspect some creative accounting going on, moving expected future profits into those funds or whatever.
So if their business models fail - e.g. due to renewables - it might turn out that in practice there never was any money set aside for decommissioning.
There are even talks about splitting off coal and fission plants into some sort of "bad bank" companies.
So I would be very wary of any such promises of things being priced in.
Corporations have again and again proven to be very good at privatizing profits while externalizing costs.
https://en.wikipedia.org/wiki/Nuclear_Decommissioning_Author...
Current estimates for one Nuclear Power Plant Site (Sellafield): £114bn which seems A LOT!
It's not going to be representative of the decommissioning costs of modern generation II or generation III reactors.
Regardless of how much one is for or against nuclear power, i think we can all come together and agree strongly that building an air cooled nuclear reactor that uses a flammable substance as a moderator and blows exhaust out a chimney is a catastrophically bad idea.
And I don't imagine that kind of activity results in easy cleanup.
The NRC estimates costs for decommissioning a nuclear power plant
range from $280-$612 million.http://www.nrc.gov/waste/decommissioning/finan-assur.html
Cost does seem quite high right?