We're in the program. As written, it's a 10 year
lease, and there's no option to buy-out the equipment at the end. We'll see if they offer that as an option as the end of the lease approaches in another 7 years. For now though, GMP is on the hook to come and get the equipment.
I would also suggest that size and weight are bigger concerns than you're giving credit to. They aren't assembling packs on-site from individual batteries. They're rolling in whole-ass packs in one swell foop. Getting them into basements isn't a small job[0]. Getting them back out will be even less fun for the crews.
Their total on-site install time was maybe 6 hours, and that included tying everything in to the existing system. Putting the hardware in place took maybe an hour of that time. If you want to go with heavier packs or more/larger packs, you're going to add to that a bit. And their doing this in people's finished homes. This isn't new build where they can have a couple of big dudes wrangling packs around without a care in the world for furniture and finished surfaces. The ergonomics of smaller packs matter.
[0] They used a two-wheel dolly with a hydraulic disc brake (bicycle hardware) to get them down our basement stairs.