-- strangely I had never actually thought about this
-- strangely I had never actually thought about this
> Additionally, many residents who live near AI data centres are seeing increased electricity bills due to the amount of electricity those data centres use.5 That's right, trillion dollar companies are using you to subsidize their power bill!
I'm glad the author put this paragraph early into this article though. Saved me a few minutes reading the rest.
There is a root issue here: prices of nonrenewables don't incorporate the costs of climate change. But that's a much broader issue, and otherwise the market price system is excellent at allocating energy to its most economically beneficially uses.
No, because that solar farm would have never been built in the first place without the datacenter. You either get both or you get none of them. It's completely different than using an existing solar farm that was already there before anyone started planning for that datacenter
"most renewables are sited so poorly that it likely doesn't reduce CO2 emissions at all" -- source?
The problem with this essay is thinking power demand is bad. It is not when we can deploy massive amounts of renewables. Not only for AI, but for other industrial workloads that user power.
If the rest of the dipshits around here hadn't elected the dumbest mother fuckers on earth, we'd be pushing out subsidies to build out renewables at 10x the rate we are now. But hey, coal jobs matter.
Funny how this line of thinking is indistinguishable from crypto.
> It is not when we can deploy massive amounts of renewables. Not only for AI, but for other industrial workloads that user power.
Funny how this line of thinking is indistinguishable from crypto. "Yes, we build a lot o power which is immediately consumed by us, but see how this is good? See? SEE?!"
> we'd be pushing out subsidies to build out renewables at 10x the rate we are now.
And these would be gobbled up by crypto and AI data centers, right?
https://www.itpro.com/infrastructure/data-centres/gas-powere...
"Traditional hubs are at or near saturation, which has created long connection queues with waits of typically seven-to-ten years and in some cases 13-15. The International Energy Agency (IEA) estimates that globally, nearly 20% of planned data center projects risk delay due to grid bottlenecks, and as a result developers are building ‘behind the meter’ primary generation. This offers speed to market in months rather than years.”"
"gas is mainly chosen because it’s the fastest and easiest way to generate your own power. Turbines and engines can be set up and begin providing reliable energy quickly, while renewable power generation can be intermittent without costly storage – and takes time and money to be set up."
https://www.greengasturbines.com/blog/gas-turbines-for-data-...
"Global data center electricity consumption is projected to more than double by 2030, driven primarily by AI training and inference workloads. The IEA estimates data centers could consume over 1,000 TWh annually by 2030 — roughly equal to Japan's total electricity consumption."
"Grid interconnection queues are now 4–7 years in many US markets, making behind-the-meter gas turbine generation the fastest path to powering new hyperscale campuses."
"Microsoft, Amazon, and Google have all signed gas turbine power agreements or acquired generation assets in 2024–2026, signalling a structural shift in how hyperscalers think about electricity procurement."
"The gas turbine data center trend is not temporary. Even as renewable procurement grows, the intermittency gap and the sheer scale of AI power demand mean firm, dispatchable generation will remain essential for Tier III and IV reliability standards."