During my tenure there, we went from continuous ~2MW to ~3.5MW (5MW designmax). Certain days of the year we would spend hours just shedding load with our on-site 1MW loadsink/"toaster", being paid by PowerCo to burn off their excess baseload. This cut our energy bill in half (despite using even more energy!). Hopefully battery grid storage has reduced this practice..?
On those days our entire cooling yard would exceed 130°F (asphalt surface, primarily). Semi-arid Texas, otherwise, at a balmy 102°F.
> The research exaggeration pipeline.
>
> -Unpublished paper
> -One outlier: "min & max can be found at 0.3°C and 9.1°C" (95th pct "between 1.5°C & 2.4°C")
> -No causal identification; just pre/post that could be result of many factors
>
> Do you really believe data centers are warming 10km away? Really?
https://bsky.app/profile/brendannyhan.bsky.social/post/3mi7i...
https://blog.andymasley.com/p/data-centers-heat-exhaust-is-n...