But that also applies for the current generation of reactors and nobody can build them to schedule or budget in the USA or Europe.
The NRC frequently changes requirements for reactors while they're under construction. The NRC does not waive the right to demand changes merely due to prior design approval. This is a novel (for the US) design, so there will be unanticipated changes as the project progresses.
Russia has been operating two sodium cooled fast reactors for decades. The BN-600 and BN-800 are both operating today. The early history of the BN-600 was... interesting, suffering (at least) 14 sodium fires due to leaks. This "Natrium" design is similar; a sodium pool with two sodium loops. They are taking on the additional challenge of storing a massive quantity of molten salt. It's going to take a lot of effort by many steely eyed missile people to make this happen.
Trump issued an EO in 2025 that's supposed to make the NRC more circumspect about requiring changes of approved designs. Then there is all the pull Gates has. Wyoming is no hotbed of anti-nuclear activism. So that's all to TerraPower's favor. But TerraPower will need to fully utilize all the tailwind it can find to make this work.
But when that fails, you can just siphon up taxpayer money via your connections to the ruling cabal.
https://www.thedailybeast.com/tiny-trump-linked-firm-in-line...
> They’ll reverse IPO along the way and manipulate the stock enough to get insiders paid out while the carcass of a company trundles along.
I'm not sure what "reverse IPO" means, maybe you mean they'll be acquired by a SPAC, like NuScale was. I doubt it. Bill Gates founded Terrapower in 2008, he is not looking for a quick buck.
I hope you’re right and they stay focused on actual engineering instead of financial engineering but many of Gates’ other investments haven’t been so fortunate and went down the latter path. The billions of dollars in taxpayer funds and constantly shifting tech and demo projects gives me a lot of pause though. (MSR! TWR! Fast Reactor! Fujian! Hebei! Idaho! Hanford! Wyoming! UK!)
Put it this way, if it's in commercial operation by 2031 I'll eat my hat.
Even with all that experience and expertise, their questionable environmental policies and questionable worker rights, it still takes them SEVEN years to build a single nuke.
The claim that anyone else can do it faster with zero recent experience isn’t only laughable, it’s downright fraud.
Be careful with these figures. I understand they start the clock later than the west does.
Seems like we could match a 7 year clip at a much smaller scale. We'll be forced to at some point, but we need to overhaul the regulatory mess and fix the grid first. Hopefully that happens long before battalions of Chinese drones and droids take over the world.
China and Russia are about on par in build times now. Korea is next with APR, Barakah having about 8y/unit, W-house and EDF are the slowest for many reasons
Come April, all the production and construction capacity will be commandeered for the war machine.