> the power plants are delivering precisely what was planned
No. The load factor of the pair of EPRs built in China (5 years late and 60% above the budget) at Taishan is quite bad (.55 and .76).
In France the EPR isn't even producing electricity, while it was to be delivered in 2012 (budget 3.3 billions €, real cost > 23.7 billions €)
> delay and cost overruns caused by local political opposition and lack of vision
Source? An official report (dubbed the "Folz report") explains why the EPR project in France (Flamanville) was a failure, I cannot find "local political opposition" among the causes.
French ahead: https://www.assemblee-nationale.fr/dyn/media/organes-parleme...
> In France all historical reactors worked so well that we did not feel the need to build more.
The context was quite different:
https://sites.google.com/view/electricitedefrance/messmer-pl...
... and the real total cost of this "nuclearization" is already huge.
> This lead to talented engineers going to retirement without having a chance to pass on their knowledge and experience
The Civaux-2 reactor was delivered in 1999.
In 2000 the French nuclear sector (at the time "Areva") was trying to sell EPRs (even in France).
In 2003 Finland ordered an EPR and work began in 2005.
How exactly are we supposed to believe that all knowledge vanished, without anyone in the industry to act accordingly, especially while the existing French fleet of reactors (56 at the time) had to be maintained?
> our decision to put it aside for a while
Cause: oil counter-shock (~1985), which (sadly) reducing electricity competitivity
https://ourworldindata.org/grapher/electricity-generation?ta...
Even EDF, as early as 1986, considered the nuclear fleet too large: "We will have two to four too many nuclear reactors by 1990," ( https://www.lemonde.fr/archives/article/1986/01/17/nous-auro... ) and this was confirmed by the 1989 Rouvillois-Guillaume-Pellat report. The reason is well known: after the oil price shock, hydrocarbon prices had fallen significantly and sustainably, and they were competing with electricity.
However, reactors were built until the end of the 1990s. Three of them were started after 1985, and four were built in the 1990s. Some were ready to go in 1999 but did only diverge the generate electricity in 2002...
> certified for a lifespan of 60 years
Subject to a successful technical in-depth inspection every 10 years.