It’s fairly obviously designed to avoid the issues which almost caused the cancellation of the new Edinburgh tram — spiralling costs caused by the need to move existing utilities under the deep track base. That crisis was probably as much to do with a badly formed set of contracts as with the technical issues themselves, but it’s still worth designing out.