French nuclear plant consumes more power than it generates in first two months
energy-charts.info
energy-charts.info
I'm not an expert but to me it looks like they are still in some kind of testing/verification/certification phase? According to its operator's website[0] they ran into some minor technical issues during ramp-up, which of course have to be fixed as well.
The alternative is going into full production before testing has been finished, but that's how we got Chernobyl. I'd rather have it operate at an energy loss for a few months so they can carefully work out all the teething problems than have it irradiate a decent bunch of France and England.
[0]: https://www.edf.fr/la-centrale-nucleaire-de-flamanville-3-ep...
Following this initial coupling, in accordance with the startup operations, the phases of testing and of connection and disconnection to the grid will continue for several months, under the supervision of the ASN, until the reactor reaches 100% power.
- it's hardly a "new" or relatively modern design considering this particular design goes back to the mid 1980's, being designed by SIEMENS in France, and the first one (Finland) went online twenty years ago in 2005.
Five EPRs have either been built or are being built; another one is planned. Four of the five EPRs built have suffered enormous cost overruns and/or significant construction delays.
The Taishan 1 reactor in China, the first to be completed, was taken offline in July 2021 because of damaged fuel rods.
Source: Institute for Energy Econoics and Financial Analysis
https://ieefa.org/resources/european-pressurized-reactors-ep...
https://www.mdpi.com/2071-1050/14/12/7098#
(Link broke, try this one: https://pub.mdpi-res.com/sustainability/sustainability-14-07...)