A chip fabricator cannot run off intermittent power. It can't shutdown quickly, nor safely.
France recently went weeks with every single nuclear power plant in the country offline, but the system was designed to cope with such downtime.
At the beginning you can get great uptime but eventually you face years like this: https://www.worldnuclearreport.org/IMG/pdf/wnisr2022-figure2...
Of those 56 reactors in the entire of 2021 no more than 49 where on online at any time in the same day. 90% of the time it was 46 or less. 16% of days it was 36 or less bottoming out at 28, and everything didn’t suddenly start working in 2022.
https://www.worldnuclearreport.org/IMG/pdf/wnisr2022-figure2...
That’s the reality of “dependable” nuclear power, it wants to run 24/7 but can’t run 365.