This article is about a power plant that cost £46Billion and nameplate of 3260 MW
Assuming 100% load factor for the plant (looks like 70-80% is more common but I'll be generous) that's 28,557,600MWh per year. Or a cost of £1610 per MWh per year.
Taking just one of the latest wind farm in UK South Kyle Wind Farm, Cost £38Million with a nameplate of 240MW.
Assuming 10% load factor (30% is common but I'll be pessimistic for this case).
That's 210,240MWh per year,(2400.1 24 * 365) that's £180 per MWh per year, (Life span differences of wind(30 year expected) vs nuclear(40-60) could increase the cost of the wind by up to double if you took the worst case but I've already given a 3x disadvantage on load factor) Even with the deck stacked in nuclear's favour it's 10x more expensive than wind, you will simply never migrate a factory using thermal gas with the cost of electricity made by nuclear.
Edit: also Flamanville 3 in france costs are better but still so much worse than wind, 13billion Euro(~11Billion GBP) for 1600MW nameplate, comes out for 713gbp per MWh per year, still 3x worse than wind.