Which brings up another reason why some of these projects were Fast -- they operated in places where there there wasn't existing infrastructure or residents to deal with, or cut corners on planning and mapping, which future projects now have to deal with.
https://sfstandard.com/transportation/van-ness-brt-bus-rapid...
Immediately after breaking ground, construction delays began. Existing maps of old gas, water and sewer lines flowing beneath the center of Van Ness Avenue proved inaccurate, slowing excavation and causing the city to bring in utility contractors. The utility placement also made the BRT’s center-lane design a challenge: Any future sewer and water repairs would disable bussing for the duration of repair. Plus, overhead bus electrical wires would need to be fully removed for the safety of the crews. Water and sewer infrastructure needed to be moved to the outside lanes to keep the center-lane BRT design — deemed the best for traffic flow.