Somehow this estimation is taken at face value, and yet:
> Hinkley Point C is a 3.2 GWe nuclear plant and is currently estimated at 32.7 GBP
This is taken at actual value. Even though original cost was estimated at 12.4 bn GBP. A lot of cost and budget overruns for nuclear plants are purely political, amidst a rising ocean of FUD.
Meanwhile, https://www.offshorewind.biz/2016/12/02/offshore-wind-projec...
--- start quote ---
Ernst & Young (EY) has found that an average power and utility megaproject is delivered 35% over budget and two years behind schedule
Of the megaprojects surveyed, 64% were delayed and 57% were over budge. Almost three-quarters of hydropower, water, coal and nuclear infrastructure projects were over budget by 49% on average,
--- end quote ---
So that estimated 16bn GBP is very likely to be significantly over 25bn GBP by the time it's completed.
Edit.
More:
https://percepto.co/solar-construction-delays-budget-overrun...
"Data shows the avg. 50MW PV construction project delays cost $2M. The average solar construction project is delayed by about 20% with the consequences hovering around $2M in costs."
https://www.qualenergia.it/sites/default/files/articolo-doc/...
"we assessed the construction costs affiliated with 401 electricity infrastructure projects worldwide. We found that these projects collectively involved $820 billion worth of investment, and represented more than 325,000 MW of installed capacity and 8500 km of transmission lines. Taken together, these projects incurred $388 billion in cost overruns, equivalent to a mean cost escalation of $968 million per project, or a 66.3 percent overrun per project."
And so on.