I enjoy that their recourse for such a failure in design so far has been to "write a strongly worded letter". Is there some kind of protection for the builder that is preventing them from being sued? Is the airport body governing this actually the one that failed? What a bizarre situation
It appears the 4/20 work with smaller planes, so merely may not have been need until now.
Local reporting has a few other issues mentioned about specific gates, which to me sounds like a "Our contract says you have 30 days to reply to our letter informing of issues before xyz happens". So purely posturing before mediation before lawsuits. But we'll see.
For anyone interested, I found the local media coverage was higher quality: https://www.seattletimes.com/business/boeing-aerospace/sea-t...
> ... the Port is counter-suing Clark to recoup costs involved in fixing the gate layout fiasco.
I used to be a civil engineer and for the earthworks the PE always had us checking things. especially grades in the areas around the perimeter. Our initials were on it but the PE stamped it. We did catch a few things where the plans called for a "wall" because if we did our 3/1 grading we'd meet existing over the property line.
Not sure how the engineering works for airports.
> “The Port is now identifying modifications to gate design based on operational considerations that were not contemplated in the program requirements in our contract,” [a Clark Construction representative] wrote.
> Clark’s latest legal brief, filed in late February, asserts that the contract documents defining the work “specifically state that Clark was to design the Project to accommodate narrowbody aircraft at Gates A6 and A8, not widebody aircraft.”
https://www.seattletimes.com/business/boeing-aerospace/sea-t...
What wasn't in sync was the ports "general ideas" about what they wanted from the transaction and the technical requirements they produced attempting to encode those "general ideas". Unfortunately there's not a great way to validate those, at least that I see. Pay for a better engineer to sit in on your years of meetings rambling about what the "future of the port" will be?