is that the LGV Sud Europe Atlantique between Tours and Bordeaux that opened in 2017? looks like thats €9B for 188 miles new track or €47M per mile.
https://en.wikipedia.org/wiki/LGV_Sud_Europe_Atlantique
> The consortium invested €3.8 billion, French government, local authorities and the European Union paid €3 billion and €1 billion was contributed by SNCF Réseau (subsidiary of SNCF). Another €1.2 billion was spent by SNCF Réseau on the construction of interconnecting lines, control centres, capacity enhancements at Bordeaux and remodelling the track layout at Gare Montparnasse.
A "bright line" style upgrade to the SAN-LAX route would have been entirely worth it, and they're struggling along with it, but at pennies compared to what has been spent on HSR so far.