The LVCC Loop started boring in 15 November 2020 and opened to the public on 15 April 2021 - so 5 months, for the 2.7km. The Channel tunnel began construction in June of 1988 and opened for freight trains in June of 1994, so 72 months for the 50.4km.
So, the LVCC was built at 0.54 km/month, while the Channel tunnel was buildlt at 0.7 km/month.
Which part is false?