Current gen LWRs are problematic for all sorts of reasons but i wouldn't rule nuclear out of the fight just yet. Especially when you take into account china's track record of delivering nuclear plants at a competitive price.
Current gen LWRs are problematic for all sorts of reasons but i wouldn't rule nuclear out of the fight just yet. Especially when you take into account china's track record of delivering nuclear plants at a competitive price.
> An academic reactor or reactor plant almost always has the following basic characteristics: (1) It is simple. (2) It is small. (3) It is cheap. (4) It is light. (5) It can be built very quickly. (6) It is very flexible in purpose. (7) Very little development will be required. It will use off-the-shelf components. (8) The reactor is in the study phase. It is not being built now.
>On the other hand a practical reactor can be distinguished by the following characteristics: (1) It is being built now. (2) It is behind schedule. (3) It requires an immense amount of development on apparently trivial items. (4) It is very expensive. (5) It takes a long time to build because of its engineering development problems. (6) It is large. (7) It is heavy. (8) It is complicated.
SMRs and MSRs are in the academic stage at the moment. We don't know what they will look like at the end when they are actual products, but there are technical and practical reasons that they haven't been tried before now, so I think it's only prudent to withhold enthusiasm until we have data on their characteristics and potential.
Back in the 80s, we had PV panels in hand, and knowledge of silicon tech curves that could predict the rosy future we live in today. SMRs are a bit more shaky.
Multiple sites are planning for their use, both in the United States and elsewhere: https://www.nuscalepower.com/Projects/Current-Projects/Unite...
NRC approval doesn't say anything about constructability or economics. It doesn't even say much about the operating characteristics, except that the NRC is pretty sure it meets the safety guidelines.
This is why there are these characteristics that Rickover lists, which NuScale will encounter when they finally build, but are not revealed by any planning they have done up until now:
> (1) It is being built now. (2) It is behind schedule. (3) It requires an immense amount of development on apparently trivial items. (4) It is very expensive. (5) It takes a long time to build because of its engineering development problems.