> what do you recommend if we find a pattern where at the end of each week, we made maybe 25% progress on that weeks commitments? Dates committed by the team itself - not forced on them from the outside or management.
I'd typically handle this in a weekly sprint call, or during 1on1s.
I'd typically take responsibility for my team's missed deadlines too, as there's almost always something more management can be doing to make their teams successful (barring bad faith performance from an employee, which deserves a different conversation).
If it was an honest missed deadline, I might say something like: "Hey team, I know we missed the deadline and that's had [this specific impact] on us and [this specific impact] on our client. I want to apologize because I should have caught this delay sooner. I also want to offer up [suggestion 1] and [suggestion 2] as ways to get back on track. But I'm open to other ideas as well."
Obviously, there's nuance to every situation and that isn't a 1 size fits all, but it's a general theme I'd typically use.
Some suggestions I'd typically offer were:
* Reallocating complex tasks from Jr. members to more Sr. members
* Reducing the scope
* Offering to help personally with some tasks
* Bringing in additional resources
* Revising our expectations for next week
> It killed morale for the few of us that were focused on delivery. We all left the team over it, and 6 months later the team was re-org’d.
Yep, I've seen this happen myself too. Sorry you went through it. I hope the move was a good one for you. In my experience top-performers really don't like it when other team members bring the speed / strength of the team down. It totally kills morale. But, I do put a lot of that responsibility on the manager. They should see this happening and adjust before the top performers get annoyed.