Install labor is relatively cheap but more importantly flexible - relative to the cost of the project install is low double digits %. If a job isn't running smoothly you cut your temps and move your main crew over to another site or send them home if they're local. I would wonder how this work fit in with an automated build/install solution.
Unless you have control at the GC level you're going to be start/stop with electricians cutting trenches in front of you, missing materials (tariffs/port strikes), permitting delays, etc, and you'll have expensive idling equipment that's tough to move.
I get that this is the problem you're trying to solve - but I'd definitely suggest going to enough bread and butter 2-10MW sites where this sort of thing is more common. Also keep in mind Central CA in summer is not Massachusetts in November, weather makes all this 10x worse.