Most of the existing HVDC interconnects are undersea.
You don’t need to deal with 10k different landowners each wanting their own special deal if you’re connecting Tunisia and Spain, vs North and South Germany.
Most utility corridors are in the middle of nowhere and already established (and people stay away because of this), so reusing an existing corridor is relatively easy - unless it widens into someone’s yard. Then it’s a matter of how much money that person has.
For connecting previously not connected areas with a new line, especially if it goes through somewhere folks are living? Be prepared for the actual work making whatever you are doing to be a tiny tiny percentage of the time and costs involved.
You can't take the experience of a private citizen trying to clear some brush, bridge widening delays in one of the most regulation heavy states in the country, and oil pipeline opposition, and apply it to building HVDC between countries in Europe.
Unlike your examples, HVDC lines have no real negative impact on anyone but the immediately impacted property owners. If you're building HVDC transmission lines between countries, you can also very likely reuse existing utility corridors for much of it, and build through lower density areas for most of the rest. The actual number of property owners directly impacted won't be high enough to make an impact on elections.
Or some random place in Ohio for that matter.
The regulatory hell that cities and states wealthy enough to afford it impose on themselves is not representative of the entire country.
Europe is at least as regulation heavy as California.
HVDC is (I think) the only thing that can be used for underwater connections, so it’s used where the price makes sense. If the question is regulation we should also see all proposed and recent AC lines in Europe.
(Edited for clarity)
Yet essentially all planned or existing HVDC lines (at least ones notable enough for the map), are undersea cables.
Why would that be?
There are definitely undersea HVAC interconnects - https://www.nkt.com/products-solutions/high-voltage-cable-so...
They seem non-notable enough I had a hard time finding a good combined list anywhere.
I ran across plenty of references to HVAC being used for offshore wind turbines and the like too.
And they were the default standard (and still are for shorter runs and where the grid frequency matches). There are AC solutions for lack of grid frequency matching and the like.
I can’t find a list or easy map for major new on land grid connections - if you can find one, that would be great. Might be national security concerns or something?
If it’s a 1000km single run, the math is definitely different, but there aren’t a lot of those. If there are transformers, taps, generators, or other live equipment in the middle, those also change the equation, and in a grid environment, there are a ton of those.
I know of at least one such solution between Germany and Sweden trough the Baltic Sea.
edit: This https://en.wikipedia.org/wiki/Baltic_Cable
I found this neat paper on HVDC grounds and interconnects too [http://b-dig.iie.org.mx/BibDig2/P13-0399/files/PESGM2013-001...]
The point is that right of ways and permits are super hard on land, which is why most of these are run via the sea.
Even in the US (which is very low density compared to most places), most people live in cities or denser suburban areas (80.7%). 97% of all land Area in the US however is Rural.
So you are right in that this is not a problem in most of the US (by land area), and this isn’t a problem in elections in those areas either - it won’t negatively impact enough individuals, and problem cases can often be routed around, because the pop density is low.
However, this IS also a problem for most of the US (by populations), as this directly impacts costs and infrastructure upgrades for the majority of the population in the US.
Europe is even denser, and some locations have just as bad if not worse regulatory environments, so it’s the same factors at play. Some countries in Europe excepted of course.
If you’re covering significant distances that people live in, you can expect to spend a decade or sometimes more in court before being able to build - if ever.
Because of course there are the environmental reviews, the impact assessments, etc. and each of those will be hundreds to thousands of pages long, and you’ll likely have to fight over each page, also in court, with folks who don’t like that you’re going to dig up that random patch of flowers to install your power line or whatever.
And that is assuming you’re lucky enough to not have any endangered species in the way, in which case you might literally not be able to build at all if it is in an area you have no choice to go through.
So far no one is staking out patches of ocean floor, and generally even if they did, the topography is usually more forgiving there. So all you need is landing approval, which means one government and one compliant landowner on each side somewhere along each coast that is close enough to an existing grid that you can interconnect to it. Much more solvable. Still not easy or straightforward.
In California it took me 4 years and $18k worth of professional help to get approval to do completely standard fuel reduction work on a completely uninteresting plot of land that was super overgrown with brush and dead trees - with no one objecting to it - in the middle of a historic wildfire crisis in California that actually expedited the process.
I had to notify 10 something local native tribes (in case they maybe were somehow attached to the land, which they weren’t), had to do a detailed archeological survey, had to have a licensed biologist do a detailed walkthrough to look for endangered species (there were none).
Meanwhile the 3 largest fires in the states recorded history burned nearby, and they wouldn’t let me clear brush and remove dead trees from a clear fire hazard area and it’s a miracle the place didn’t burn to the ground.
The details will have to speak for themselves and this is not the forum, however I strongly encourage you to seek some kind of outsider, and avoid those for whom the reputational damage occurs..
I got my thing approved and done with (finally), zero interest in getting involved any more. Everyone else involved knows this is how it goes too.
If you think me going to some news agency is going to do anything but get me stomped on in some future year (and it ending up being a decade instead), you might want to take a look around first.
edit: all these records and more are also public records and should be trivially available via FOIA requests - which said PRcoughnews outlets would be pulling if they wanted to know what was really going on.
There are only 100k private timberland owners in CA (and mostly nutballs like myself that seem to like pain and suffering in the form of paperwork), so it’s an easy group to stomp on, relatively speaking.
Oil pipelines are bit different because there are tons of people and organizations outside of those directly impacted who are willing to join the fight.
You can remove small amounts of nuisance stuff in small areas, and burn in small piles during days you are approved to burn (which are limited). Maximum pile height of 3 ft, and 3x3 ft diameter if I remember from the last burn permit I pulled?
You can clear up to 1/3 of an acre, or emergency thin I think up to 3 acres if you comply with those rules, but the 3 acres they reserve the right to come in and fine you if you do something they don’t like, and you have to file a permit to do that too. Any trees about a certain diameter or of certain species, regardless of level of disease or danger they might require you to keep. A dead tree that might have an owl or protected animal in it? Ho boy.
It would take several lifetimes to even attempt that on 60+ acres of overgrown timber. I spent a week and barely did 1/4 of an acre working full time, and it still wasn’t adequately thinned.
In the end, it took a crew of 4 with purpose built heavy equipment (a masticator), working full time over 4 months to do it to state standard -once the paperwork finally cleared this summer.
Each one of which has some plausible reason for it to exist that nominally make sense, but starts of choke out a ton of reasonable behaviors pretty quickly.
See http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.981...