Essentially, this is what the nuclear phaseout entails; old plants are decommissioned and governments refrain from subsidizing the construction of new ones.
Essentially, this is what the nuclear phaseout entails; old plants are decommissioned and governments refrain from subsidizing the construction of new ones.
Why that? In France nuclear power plants are kept to the newest safety standards. Everything in a nuclear power plant can be replaced apart from the reactor vessel and the containment building.
Nuclear isn't working very well in France either. The reactor in Flamanville had an initial projected cost of 3.5 billion euros which has now ballooned to 12.4 billion euros and the project is over a decade late. https://www.reuters.com/article/us-france-nuclear-idUSKBN24A... The French are also preparing to transition away from nuclear as more plants are being decommissioned.