A little anecdote, here in Cincinnati I was peripherally involved with a local nonprofit taking over management of an abandoned bit of city part to build new multi-use trails. It took 20 years for the park board to even listen, then once an agreement was reached it took another /year and a half/ to get the paperwork to the point where they would officially sign it. Just for a group to build trails, with no money needed from the city, no permits, etc.
Projects like what sidewalk labs was trying to accomplish frequently take 5-10 years+ to get anywhere. Planning in the US is absolute garbage. It is a big part of the reason SF and other large US cities are so expensive. Luckily there are some groups like YIMBY making headway here.
This is why it took a long time. The city was handing over management over part of itself in perpetuity. That needs to be done with care and deliberation.
Moreover, there are liability issues related to third parties making alterations to city lands that could result in ruinous liability to the city if citizens get injured on the altered lands and the city didn't fully inspect the alterations.
You also have potential drainage and soil issues to deal with, which need to be reviewed by geologists. And that's not getting into environmental reviews if there are at-risk species dwelling in that park.
All of those things take time. Programmers always complain about their customers wanting X in a few weeks when it really takes months.
So why are programmers always complaining that it takes engineers, geologists, architects, and city planners months to do their jobs? Unlike programming, the stuff these professionals are doing/reviewing can't just be fixed with a patch.
I'm not sure if SWL's plan would have worked in conjunction with that work or if they would have overridden it.
The city has the right at any time to revoke the MOU between the city and this group, so there wasn't really risk there. I understand that care should be taken, but at a certain point you begin having serious inefficiencies.
>Moreover, there are liability issues related to third parties making alterations to city lands that could result in ruinous liability to the city if citizens get injured on the altered lands and the city didn't fully inspect the alterations. This is through an IMBA chapter which accepts all liability and responsibility and includes insurance coverage. This is not some new, unique thing that is happening. There are many dozens if not hundreds of these agreements in place in other cities already.
>You also have potential drainage and soil issues to deal with, which need to be reviewed by geologists. And that's not getting into environmental reviews if there are at-risk species dwelling in that park. There aren't major structures being put in place, and most of the parks around here have very, very degraded ecosystems except in a few notable, well known locations.
>All of those things take time. Programmers always complain about their customers wanting X in a few weeks when it really takes months.
>So why are programmers always complaining that it takes engineers, geologists, architects, and city planners months to do their jobs? Unlike programming, the stuff these professionals are doing/reviewing can't just be fixed with a patch. For what its worth I'm an electrical engineer, not a programmer, that deals more with manufacturing. My last job involved electronics for explosive atmospheres that were expected to last 10+ years minimum, so I have a good understanding of not being able to quickly send out fixes with a patch.
The process wasn't really transparent, so it really felt like people kind of dragging their feet and being very resistant to change. Something my city is known for (see famous Mark Twain quote about Cincy and the end of the world). I understand very well taking months to do things, but years for something like this is maddening.
On that sort of timescale, that's less down to "things move slowly" and more down to "you can't get anything done in the wrong political climate, so you have to wait until appointed officials die and/or an entire generational shift in your municipality produces a sea-change of political views."
So, basically, any municipal political plan that involves "waiting the problem out" as a strategy, should never actually be chosen/pursued, because if time has any associated overhead costs, then the indefinite amount of time required will cause the overall strategy to have predictably negative ROI.