How much time it took you to build first version and whole product? Any advice for starters?
How much time it took you to build first version and whole product? Any advice for starters?
May 3 2013 - Started development Flask website & Vim plugin (https://wakatime.com/blog/1-why-i-built-wakatime)
June 25 2013 - Finished Vim plugin and Website (https://github.com/wakatime/vim-wakatime/commit/4346a055e301...)
July 1 2013 - Started Sublime plugin (https://github.com/wakatime/sublime-wakatime/commit/b7fe36f8...)
July 15 2013 - Finished Sublime plugin and public launch (https://news.ycombinator.com/item?id=6046227)
Unfortunately I don't have WakaTime data until after finishing the Vim plugin, but everything after that I can see how long the actual coding took by dogfooding.