Pointing stories/tickets/units-of-work should not be tied to time estimates [0]. It should be a tool to break down useful deliverables into the smallest useful deliverable, leading to less unknowns. Example: a task of "move application from vm to kubernetes" could be reduced to smaller parts that give the business greater insight into its progress. Maybe you have to get it working in docker first, maybe update the integration test environment, update the build pipeline, and maybe have a roll out strategy. Maybe any of those need to be finer grain. The pointing of the original story might show that the story is large and it can lead a discussion on breaking it down. Again, this is all to provide visibility to the business side. It gives them more confidence in you and your team compared to "we are still working on it."
[0]: if your team trends to a consistent velocity of points, it can be tempting to start equating points to time. Avoid this.