https://www.siemens.com/press/pool/de/pressemitteilungen/201...
That's a long enough line to stretch between California and East Coast states.
Getting rights-of-way for big interstate transmission projects is harder than actually building the projects after those rights are secured. Superconducting cables can carry more power per cross section than HVDC lines, but they're a lot more expensive and immature. Nobody has yet found a project that would justify full-scale superconducting lines over more conventional high voltage lines built with ordinary resistive conductors.
https://pv-magazine-usa.com/2018/07/09/eia-examines-hvdc-for...
It's an infrastructure investment that would pay dividends, but requires getting through a quagmire of politics.