The big issue is really setting up manufacturing and supply chain on a large scale when you do get it working.
The big issue is really setting up manufacturing and supply chain on a large scale when you do get it working.
We're building prototypes of a complex bit of consumer electronics for consumer testing. We can do full industrial design, mechanical design, electronic design get the components made, assembled and delivered in 6 weeks. The fundamental limiting factor on how fast we can do it is the time it takes for the PCB to be made. From an electronics point of view, schematic capture and layout can be done in a week, and board assembly can be done in a day (if you're in a hurry) but there's nothing we can do about the 3 week lead time on the PCB because it's 8 layers with blind laser drilled vias.
Having an engineer who would otherwise be billed out at $150 - $200/hour hand placing parts and soldering boards is a waste of our in-house resources.