Ask HN: Software project - too big scope too little time, what are the options?
estimated development workload: 3000 man/days team size:technical lead, 4 database designers, 4 application designers, 9 developers, unknown number of testers. available time: 5 months
The team was brought together from all sides a month ago. Team quality is "usual" (half is quite experienced - half interns). Four members of team have substantial experience in the field (3 application designers and technical lead). Other members of team have no experience in the field.
The team's opinion is that optimistic ETA for delivery is 12 months (with p~0.7), unless scope is cut. TPTB declare that this is not an option and are willing to pursue various arcane options (basically throwing money at problem).
The team estimates that max. 30% (you are allowed to assume 50%) of projected scope is subject to potential replacement with "off the shelf" components where the most optimistic scenario is assumed to cut the time spent on these modules by 50% (due to evaluation, modification and integration).
What I'd like to ask is - what are your experiences in such situations? I strongly suspect that adding more people will only amplify the problem in our current situation. So I insist that scope needs to be cut or deadline needs to be renegotiated. As mentioned - both appear to be non-negotiable.
Is my reasoning flawed? What other options are there?