Offshore windfarms will be built for a record low price in the UK
theguardian.com
theguardian.com
I doubt there will be another nuclear agreement after Hinkley C, and we should be thinking more about how we can starting creating storage and/or redesigning the grid to take account of a highly-renewable production system.
Nuclear enables decarbonization about a decade sooner.
Yes, solar and wind are inexpensive when penetration is low. I'm fully in favor of them. And YES, most of the world could fully rely on them if given enough money. You do this by building enough solar power to provide electricity even during cloudy winter days then enough storage to go through the night.
BUT: The UK is high latitude. That means that during the cloudy winter, it's just not feasible to build enough PV. And building enough storage for weeks is also not feasible. So you're going to burn gas, and not get to full decarbonization, or you're going to have to pull geothermal power from Iceland or something else very expensive. Going from 0 to 20% of electricity from solar/wind is cheap. 20-50% becomes more expensive. 50 to 70% is really expensive because you have to curtail a lot.
Going from 70% renewable to 100% is insanely expensive (think of that last 20-30% as being about 5-10 times as expensive per kWh) because you have to curtail MOST OF THE TIME.
But if instead you have nuclear, you can stretch your batteries and demand-response enough that you don't actually have to curtail so much. So in a world where we care about decarbonization, even 20-30% of nuclear is very valuable.
I've done the calculation. Hinkley C, even with the cost overruns, is a bargain if you're shooting for full decarbonization.
...but a lot of greens aren't. Many are being disingenuous as they care more about stomping out nuclear than they do about fighting climate change. They don't care much that it means building more gas in the near term.
Ask yourself: is throwing away nuclear worth a decade of delay in decarbonization?
Note that in countries closer to the equator, you can get like 20-25% capacity factor with solar... You also have less seasonal variation (so need less over-build) and install costs may be lower due to cheaper labor and lower land prices (so, 25/10%, 2.5x overbuild vs 5x overbuild, half the install costs... could be factor of ~10 cheaper in 100% PV install scenario). So I think solar is going to be a huge boon to the "global south" even if they rely on it 100%. But high latitude countries like the UK and Germany would be out of their minds to shut down nuclear.
How can this be, when the plants take a decade to build and are often delayed? We could build several times as much wind power as Hinkley Point C, for half the cost, in the decade before it's actually built. Actually starting a new nuclear project in the UK could not realistically be online before 2030.
"the “exceptionally low” results of a government auction on Monday for subsidy contracts show two offshore windfarms will be built for £57.50 per MWh, way below even the most extreme predictions. The price is half of what new offshore windfarms were being awarded just two years ago."
This is really something considering where the figures came in 5 or 10 years ago, and amazing to compare against the number from 2015:
Estimated UK LCE for projects starting in 2015, £/MWh Power generating technology (Lowest 2015 figures in £)
Nuclear PWR (Pressurized Water Reactor)(a) 82
Solar Large-scale PV (Photovoltaic) 71
Wind Onshore 47
Offshore 90
Biomass 85
Natural Gas Combined Cycle Gas Turbine 65
CCGT with CCS (Carbon capture and storage) 102
Open-Cycle Gas Turbine 157
Coal Advanced Supercritical Coal with Oxy-comb. CCS 124
IGCC (Integrated Gasification Combined Cycle) with CCS 137
(a) new nuclear power: guaranteed strike price of £92.50/MWh for Hinkley Point C in 2023[49][50]) (from: https://en.wikipedia.org/wiki/Cost_of_electricity_by_source )
Also love this line towards the end of the article: "The lower the price, the more electricity generating capacity can be built. The government had allocated £240m-a-year for the subsidies but the competitive prices mean it now expects them to hit £176m-a-year at most."
Are they paying more for generation than the consumer is paying for electricity?
There was a single offshore wind farm in Denmark in the high price range, where a government that had previously decided man-made warming was a hoax suddenly reversed their direction and decided it needed the farm built quickly, ending up with a single bidder.
But in any case this has finally ended.
FYI: Not long ago, DONG won a bid on a subsidy-free offshore farm in Germany. IIRC, they have until 2020 to decide whether they're going to build it or not, but they'll have to pay a fee if they don't.
Capacity factors have been rising for years as the industry matures.