To finish projects on time, start every single step as late as possible
twitter.com
twitter.com
Wow, I just don't know what planet this employer lives on where employees supposedly _enjoy_ sitting around idle until suddenly "holy crap tight deadline must crunch to make it!" Every once in a while, fine that stuff happens, but if a job were consistently putting me in "roadrunner mode" for every project, I'd be out of there in roadrunner mode too. Preferably before the anxiety and pressure turns into burnout.
Roadrunner mode probably sounds a lot like the "crisis mode" we're all used to in most orgs, but it's actually more like supercompensation principle in all types of learning and training. You focus w/ everything you have, and then recover. Most orgs try to balance capacity, which results in this steady state of draining yet not really productive work. Theory of Constraints (which is what this thread is based on) says you should instead balance flow.
I'd put Tiago squarely in my top 3-5 list of 'People Who Get It'. I highly recommend reading the rest of his work on the subject. [3]
__
[1] https://news.ycombinator.com/item?id=6468521
Harder to follow unless I go to Medium
Think of building a four-legged chair with multiple people (A, B, and C). You need to cut the wood into legs, a seat, and a back. You need to buy wood from the lumber yard, and buy screws and glue from the hardware store. You need to sand and finish the wooden pieces. You need to assemble the pieces with screws and glue.
The naive approach would be to have everyone go buy materials (and wait for everyone to get back), then together cut the wood (and wait for everyone to finish cutting), then together finish the wood, then together assemble the chair. This takes a longer time, because people will wait at each step, if there is any difference in task completion time between people. The length of each stage is the maximum of each individual task completion time.
The critical-path approach would be to send A to wood store. A returns and starts cutting leg 1, not waiting on B to return. B starts sanding the leg 1 completed by A, while A starts cutting the next leg, 2. C starts by finishing leg 1 after B finished sanding, while A starts cutting leg 3, and B starts sanding leg 2. Near the end, A has finished cutting the chair back, and goes to the hardware store to buy the screws and glue. A returns and starts assembling the chair as the pieces become ready.
Note how much earlier all the wood was cut in the naive approach. This is "early starting". In the critical-path approach, the cutting of each piece by A was delayed until it was needed by B for sanding. Buying the screws and glue was delayed until much later, when they were finally needed for assembly. That is because the critical path is:
(Buy Wood) -> (All Parts Are Finished) -> (Assemble Chair)
Other tasks can be delayed as appropriate, when doing so allows more resources to be spent on the critical path. I.e., wait until you are almost ready to assemble the chair before you buy the screws and glue, as time is better spent on getting those pieces finished!
I hope that makes sense.
I don't understand why people do this instead of just writing a blog post and tweeting a link to that.
All my tweetstorms of the past few weeks are "research" into a blog post I'm writing for ribbonfarm.com.
It irritates me, but I'm old.
Then, study the critical path to exclude all those "extra fat" that everybody includes in each task, assuring that the critical path is really critical, without hiding days/hours that would lead to procrastination in the critical path. Save it to an "emergency buffer".
Review if something else became the critical path. Repeat until stability arises.
Now, manage it, use your buffer when required, always take care if something else becomes the critical path (as everything will begin in the last possible time).
And, even if something becomes critical path and takes more time than required, you have some buffer...
However, I'd still argue that the problem of most people/individuals (especially as contrasted to huge organizations with loads of formal methodologies) is still delaying/procrastinating too much instead of too little. Too much pressure sucks, so is a rushed product/result compared with a carefully prepared one. So no, unless you really know very clearly what you're doing and how your plan will work out, which 99% of people have no clue about, start as early as possible, much earlier than your estimate, otherwise you'll definitely regret it. Though I acknowledge that this guy mostly talks about management methods, not productivity for individual endeavors.
1/ The key to finishing projects on time is to start every single step as late as possible (exactly the opposite of what most PMs do)
2/ First, because only progress on the critical path matters for final delivery, therefore all other starts are distractions
3/ It would be like spending hrs on a huge dinner prep by making all the side dishes, only to realize u forgot to pre-heat oven
4/ Second, starting early doesn't mean you'll finish early. Parkinson's Law: the task simply expands to fill the extra space
5/ Third, even if u do finish a step early, that gain will be wasted: next person won't be ready
6/ Starting a step early actually has all sorts of negat conseq, which is why procrastination is evolutionarily & logically a good strategy
7/ Starting early increases likelihood u don't have all info and prereqs, making rework likely (i.e. estimate blowout)
8/ Starting early increases the surface area for interruption attacks (internal & external), since u "have plenty of time"
9/ Starting early explodes the amt of lead time not spent actually working (i.e. Touch time)
10/ 70-99% of task lead time is waiting time, queueing, pending confirmation, waiting on approval, learning, rampup, setup, etc
11/ Ppl complain about estimation being hard, but it's not "uncertainty". It's them starting things early due to supposed uncertainty!
12/ But maybe the worst effect of starting early is that ppl start late anyway. Who actually begins a step before they have to?
13/ So you get worst of both worlds: a LONG plan with huge lead times, which are ignored as ppl do everything last minute. Vicious cycle
14/Last reason early starts suck, is they give illusion of safety. But Murphy doesn't hit everywhere evenly, he concentrates chaos at 1 spot
15/ Irony is this is self-reinforcing: did you hit the deadline because u executed well, or because you had excessive safety (100-200%)?
16/ So person who adds the most excessive safety is rewarded for "hitting their estimate," as if estimating and executing are independent
17/ Late starts fix all this: when the step is "released," they have barely enough time to finish if they go at full speed
18/ This pressure helps them focus, get into flow, ignore distractions/interruptions, optimize for 1 thing, get it done!
19/ Procrastination isn't an issue, because they're already behind, since u also cut their estimated lead time in half (oops!)
20/ If they finish on time it's actually a cause for celebration, and the next person can actually take advantage of the time gained
21/ The PM knows what to focus on, since u start with few steps (critical path ones) and only gradually begin new ones as late as possible
22/ Another benefit: once crit path person passes hot potato, they're free! U don't assign them new work, that would be punishing perform.
23/ Late starts also help with resource contentions (the same person doing 2 steps), esp important in cross-funct creative teams
24/ Instead of "start everything NOW!" You're saying "U must not start anything until the last poss moment. Focus on the current task!"
25/ This helps ppl not multitask, since they only have one task at any given time, and it's late!
26/ Ppl are generally happier: focus + flow + roadrunner mode (only 2 speeds, 100% & 0%) + fast results = happiness for both emp & co
27/ ANOTHER benefit of late starts: u have much better estimation data, since lead time now more closely approximates touch time
28/ 3 main results of all this: throughout (output x sales) explodes, lead time per project plummets, and huge excess capacity is revealed
29/ U read that right: earlier u start steps, the later u deliver projects, the more excess capacity you're likely to have
30/ Why? Because the almost universal response to late projects is "we need more capacity!" False. U need to use what u have
31/ The busier everyone in your co seems to be, the more confident I am that you have tremendous, double-digit excess capacity
32/ To add insult to injury, emps in such companies also say they're "too busy to invest in productivity." Speed up the hamster wheel!
33/ BUT to use late starts, u also need buffers. Bec some steps do in fact go late, just not as many and not as late as u think
34/ And I don't mean buffers as a general concept, u need very precisely placed and sized buffers divided into zones, updated daily
35/ There is a buffer for every purpose: project buffers, feeding buffers, iteration buffers, bottleneck buffers. Gotta know which 1 to use
36/ The PM's job becomes easy: just watch the buffer penetrations. No need to do anything until it gets to Zone 3 or 2, all else is noise
37/ If u want to know where all this comes from, Critical Chain Project Mgmt: https://en.wikipedia.org/wiki/Critical_chain_project_managem...
The key to finishing projects on time is to start every single step as late as possible (exactly the opposite of what most PMs do). First, because only progress on the critical path matters for final delivery, therefore all other starts are distractions. It would be like spending hrs on a huge dinner prep by making all the side dishes, only to realize u forgot to pre-heat oven.
Second, starting early doesn't mean you'll finish early. Parkinson's Law: the task simply expands to fill the extra space. Third, even if u do finish a step early, that gain will be wasted: next person won't be ready. Starting a step early actually has all sorts of negat conseq, which is why procrastination is evolutionarily & logically a good strategy:
* Starting early increases likelihood u don't have all info and prereqs, making rework likely (i.e. estimate blowout)
* Starting early increases the surface area for interruption attacks (internal & external), since u "have plenty of time"
* Starting early explodes the amt of lead time not spent actually working (i.e. Touch time)
70-99% of task lead time is waiting time, queueing, pending confirmation, waiting on approval, learning, rampup, setup, etc. Ppl complain about estimation being hard, but it's not "uncertainty". It's them starting things early due to supposed uncertainty! But maybe the worst effect of starting early is that ppl start late anyway. Who actually begins a step before they have to? So you get worst of both worlds: a LONG plan with huge lead times, which are ignored as ppl do everything last minute. Vicious cycle.
Last reason early starts suck, is they give illusion of safety. But Murphy doesn't hit everywhere evenly, he concentrates chaos at 1 spot. Irony is this is self-reinforcing: did you hit the deadline because u executed well, or because you had excessive safety (100-200%)? So person who adds the most excessive safety is rewarded for "hitting their estimate," as if estimating and executing are independent.
Late starts fix all this: when the step is "released," they have barely enough time to finish if they go at full speed. This pressure helps them focus, get into flow, ignore distractions/interruptions, optimize for 1 thing, get it done!
Procrastination isn't an issue, because they're already behind, since u also cut their estimated lead time in half (oops!). If they finish on time it's actually a cause for celebration, and the next person can actually take advantage of the time gained. The PM knows what to focus on, since u start with few steps (critical path ones) and only gradually begin new ones as late as possible.
Another benefit: once crit path person passes hot potato, they're free! U don't assign them new work, that would be punishing perform. Late starts also help with resource contentions (the same person doing 2 steps), esp important in cross-funct creative teams. Instead of "start everything NOW!" You're saying "U must not start anything until the last poss moment. Focus on the current task!"
This helps ppl not multitask, since they only have one task at any given time, and it's late! Ppl are generally happier: focus + flow + roadrunner mode (only 2 speeds, 100% & 0%) + fast results = happiness for both emp & co.
ANOTHER benefit of late starts: u have much better estimation data, since lead time now more closely approximates touch time.
3 main results of all this: throughout (output x sales) explodes, lead time per project plummets, and huge excess capacity is revealed. U read that right: earlier u start steps, the later u deliver projects, the more excess capacity you're likely to have. Why? Because the almost universal response to late projects is "we need more capacity!" False. U need to use what u have. The busier everyone in your co seems to be, the more confident I am that you have tremendous, double-digit excess capacity.
To add insult to injury, emps in such companies also say they're "too busy to invest in productivity." Speed up the hamster wheel! BUT to use late starts, u also need buffers. Bec some steps do in fact go late, just not as many and not as late as u think. And I don't mean buffers as a general concept, u need very precisely placed and sized buffers divided into zones, updated daily. There is a buffer for every purpose: project buffers, feeding buffers, iteration buffers, bottleneck buffers. Gotta know which 1 to use. The PM's job becomes easy: just watch the buffer penetrations. No need to do anything until it gets to Zone 3 or 2, all else is noise 37/ If u want to know where all this comes from, Critical Chain Project Mgmt: https://en.wikipedia.org/wiki/Critical_chain_project_managem...
https://4squareviews.com/2013/04/18/5th-edition-pmbok-guide-...
I get what he's saying, but I can't imagine adhering strictly to this would be healthy. I've waited until the last minute to finish enough projects to know how stressful and anxiety-inducing it can be, and have enough experience to know that my time estimates are never accurate.
Also, notice that as hard as everyone says estimating is, they know EXACTLY when to start on that thing they're procrastinating on to finish it just before the deadline. Could it be this interesting phenomenon is a feature, not a bug?