That doesn't make any sense. Wind and Solar PV have to be financed for probably 99% of the upfront cost. All power generation is like that - very capital intensive.
EDIT: What's that Bezos quote? "Your margin is my opportunity?" Same for renewables. Your delays are my opportunity.
IE What SolarCity is doing with their SolarBonds and the solar panel factory they bought in upstate NY.
Solar and wind aren't immune to this either. You don't want to generally build things say 10MW at a time - that would require 100 rounds of planning, regulator approval, engineering design and the like for a big utlity scale solar and wind plant. You generally do it in big chunks too. And there have been big holdups especially in getting grid interconnect.