The initial budget for the Gotthard Base Tunnel was CHF 8 billion; the actual costs are now up to about CHF 12 billion. So not exactly on budget either. :) The increased costs were because of geology (4.5%), changed requirements (6.3%), environmental enhancements (1.3%) and upgrades for rail technology and safety (8.5%).